Volkmann TFO Spindle Bolsters: Planning Flange, Nut and Lock Quantities
Vindex technical notes · 23 Nov 2026

A Volkmann twister overhaul can need a new bolster at every position in the work order while requiring new mounting hardware at only some of them. Build the quote around the fitted assembly and count the hardware separately, so maintenance knows what will be available at each position.
Start with the position list
The Volkmann TFO spindle bolster product page lists VTS 07, VTS 08 and VTS 09 as separate machine references and shows a complete-set option with a flange, nut and spindle lock. Take the exact designation from the nameplate. For each position on the work order, record the fitted bolster code or the approved drawing revision and identify the hardware shown for that assembly.
Count each part that needs replacing
With the machine stopped and isolated under the mill procedure, have maintenance check the installed hardware against the machine manual and applicable drawing. Mark each item as retained, required, or pending inspection. Keep unresolved items visible on the request so purchasing can ask for separate pricing while maintenance completes the check.
For example, a work order might call for eight bolsters, two flanges and three nuts. Those numbers describe a purchasing example. Give purchasing the positions that require each piece of hardware, and ask the supplier to write the confirmed quantities and assembly references on the quote. Check the spindle lock requirement using the same position list.
Check the quote before releasing the order
Compare the quote against the work order by component. Where a complete set has been quoted, check its contents before adding loose hardware to the same purchase. Ask for written confirmation of any interface that depends on retained parts before approving the order.
Frequently asked questions
Should the nut quantity equal the bolster quantity? Count the nuts that the approved work order calls for, then account for any nuts already included with complete sets.
How should I handle a spindle lock awaiting inspection? Mark that position as pending on the enquiry and request separate pricing for the lock if it is required for the fitted assembly.
Request domestic or export pricing
Share the machine designation, assembly reference, component quantities and destination through the quote form. For international orders, see the export country directory.